How to obtain a building permit in Luxembourg

In Luxembourg, the building permit (autorisation de bâtir) is issued by the mayor of the municipality where the project is located. Here is how the process works, and how to prepare it to avoid back-and-forth.

Author
Olivier Morvan, architect
Reading time
2 min
How to obtain a building permit in Luxembourg

When is a building permit required?

It is required for any new building, and for most works that alter an existing one: extensions, adding a storey, changes to the façade or roof, structural works, a change of use or the creation of new homes. Some minor works may only require a declaration, or none at all: the exact list depends on the municipality’s regulations.

Who issues the permit?

The mayor (bourgmestre) of the municipality. The project must comply with the general development plan (PAG), any applicable special development plan (PAP) and the municipality’s building regulations. Depending on the situation (protected area, listed building, proximity to a national road or a watercourse), other authorities may need to give their opinion.

Do you need an architect?

For most projects subject to a permit, the drawings must be prepared and signed by an architect. The architect checks that the project complies with planning rules, compiles the application and acts as the municipality’s point of contact during the review.

The steps

  1. Check the rules: read the PAG and PAP and, if needed, hold a preliminary discussion with the municipality’s technical department.
  2. Design the project: sketch, then a preliminary design that complies with the rules.
  3. Compile the application: application form, drawings (location, site plan, floor plans, sections, elevations), area calculations and any technical documents required by the municipality, such as the energy performance certificate for a new building.
  4. Submit the application to the municipality.
  5. Review: the municipality checks the application and may request additional information.
  6. Decision and display: once granted, the permit must be displayed on the site, visible from the public road, for the period required by law.

How long does it take?

It depends on the municipality, the complexity of the project and the quality of the application. Allow several weeks for a simple application, and several months if a PAP has to be drawn up or other authorities consulted. A complete application at submission is the best way to save time.

Common mistakes

  • Buying land or a property without checking its building potential.
  • Submitting an incomplete application, which triggers requests for documents.
  • Starting works before the permit has been granted and displayed.
  • Underestimating timescales in the overall project schedule.

Folia prepares and submits building permit applications for its clients, for new builds and renovations alike. Example: the Bellevue project.

This article gives general guidance. Rules and grants change and vary between municipalities: check them for your project, or get in touch.